[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108326,783,1,"单选题","某项工作是由三个同类性质的分项工程合并而成的，各分项工程的工程量Qi和产量定额Si分别是：Q1=240m3，S1=30m3／工日；Q2=360m3，S2=60m3／工日；Q3=720m3，S3=80m3／工日，其综合时间定额为（ ）工日／m3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.013",false,{"key":16,"text":17,"correct":14},"B","0.015",{"key":19,"text":20,"correct":21},"C","0.017",true,{"key":23,"text":24,"correct":14},"D","0.020","考点:单位工程施工进度计划的编制。当某工作项目是由若干个分项工程合并而成时，则应分别根据各分项工程的时间定额（或产量定额）及工程量，按如下公式计算出合并后的综合实践定额（或综合产量定额）：H=（Q1H1+Q2H2+Q3H3+…+QnHn）\u002F（Q1+Q2+Q3+…+Qn），代入数据，得综合时间定额为0.017工日\u002Fm3。参见教材P127。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]