[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108325":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108325,783,1,"单选题","下列属于编制施工总进度计划的工作内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定施工场地范围",false,{"key":16,"text":17,"correct":18},"B","确定各单位工程的施工期限",true,{"key":20,"text":21,"correct":14},"C","计算劳动量和机械台班数",{"key":23,"text":24,"correct":14},"D","确定各分部分项工程的相互搭接关系","考点:施工总进度计划的编制。施工总进度计划的编制步骤和方法：计算工程量、确定各单位工程的施工期限、确定各单位工程的开竣工时间和相互搭接关系、编制初步施工总进度计划、编制正式施工总进度计划。参见教材P124",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]