[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108324":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108324,783,1,"单选题","单位工程施工进度计划编制的依据不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工总进度计划",false,{"key":16,"text":17,"correct":14},"B","合同工期或定额工期",{"key":19,"text":20,"correct":21},"C","分部工程施工方案",true,{"key":23,"text":24,"correct":14},"D","气象资料","考点:单位工程施工进度计划的编制。单位工程施工进度计划编制的主要依据有：施工总进度计划；单位工程施工方案；合同工期或定额工期；施工定额；施工图和施工预算；施工现场条件；资源供应条件；气象资料等。参见教材P126。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]