[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108322,783,1,"单选题","监理工程师在审查施工进度计划时，发现问题后应采取的措施是（ ），并协助承包单位修改。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向承包单位提出书面修改意见",true,{"key":16,"text":17,"correct":18},"B","向建设单位发出工作联系单",false,{"key":20,"text":21,"correct":18},"C","向承包单位发出整改联系单",{"key":23,"text":24,"correct":18},"D","向承包单位发出停工令","考点:建设工程施工进度控制工作内容。如果监理工程师在审查施工进度计划的过程中发现问题，应及时向承包单位提出书面修改意见（也称整改通知书），并协助承包单位修改。参见教材P121",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]