[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108318,783,1,"单选题","下列不属于确定建设工程施工进度控制目标的依据的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理合同中有关工期的要求",true,{"key":16,"text":17,"correct":18},"B","类似工程项目的实际进度",false,{"key":20,"text":21,"correct":18},"C","工程难易程度",{"key":23,"text":24,"correct":18},"D","工程条件的落实情况","考点:施工进度控制目标的确定。确定施工进度控制目标的主要依据有：建设工程总进度目标对施工工期的要求；工期定额、类似工程项目的实际进度；工程难易程度和工程条件的落实情况等。参见教材P118",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]