[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108313":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108313,783,1,"单选题","在工程建设设计进度控制计划体系中，需要考虑设计分析评审的工作时间安排的进度计划是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","各专业详细的出图计划",false,{"key":16,"text":17,"correct":14},"B","施工图设计工作进度计划",{"key":19,"text":20,"correct":21},"C","初步设计工作进度计划",true,{"key":23,"text":24,"correct":14},"D","设计作业进度计划","考点:设计进度控制分阶段目标。为了确保工程建设进度总目标的实现，并保证工程设计质量，应根据建设工程的具体情况，确定出合理的初步设计和技术设计周期。该时间目标中，除了要考虑设计工作本身及进行设计分析和评审所花的时间外，还应考虑设计文件的报批时间。参见教材P113。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]