[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108312,783,1,"单选题","如果在已施工的部分发现一些问题而必须进行工程变更的情况下，也会影响设计工作进度，这是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设意图和要求改变的影响",false,{"key":16,"text":17,"correct":14},"B","设计各专业之间协调配合的影响",{"key":19,"text":20,"correct":21},"C","工程变更的影响",true,{"key":23,"text":24,"correct":14},"D","材料代用.设备选用失误的影响","考点:影响设计进度的因素。工程变更的影响：当建设工程采用CM法实行分段设计、分段施工时，如果在已施工的部分发现一些问题而必须进行工程变更的情况下，也会影响设计工作进度。参见教材P114",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]