[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108311,783,1,"单选题","下列选项，不属于确定建设工程设计进度控制总目标时的主要依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计工期定额",false,{"key":16,"text":17,"correct":14},"B","工程项目的技术先进程度",{"key":19,"text":20,"correct":14},"C","建设工程总进度目标对设计周期的要求",{"key":22,"text":23,"correct":24},"D","设计费用",true,"考点:设计进度控制分阶段目标。确定建设工程设计进度控制总目标时，其主要依据有：建设工程总进度目标对设计周期的要求；设计工期定额、类似工程项目的设计进度、工程项目的技术先进程度等。参见教材P111",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]