[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108310,783,1,"单选题","工程建设设计阶段进度控制的最终目标就是按质、按量、按时间要求提供（ ）文件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初步设计",false,{"key":16,"text":17,"correct":14},"B","技术设计",{"key":19,"text":20,"correct":14},"C","建筑设计",{"key":22,"text":23,"correct":24},"D","施工图设计",true,"考点:设计进度控制分阶段目标。建设工程设计阶段进度控制的最终目标是按质、按量、按时间要求提供施工图设计文件。参见教材P111",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]