[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108308,783,1,"单选题","工程设计要划分为初步设计和施工图设计两个阶段，特别复杂的工程设计还要增加（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初步设计审核阶段",false,{"key":16,"text":17,"correct":14},"B","施工图设计审核阶段",{"key":19,"text":20,"correct":14},"C","扩大的初步设计阶段",{"key":22,"text":23,"correct":24},"D","技术设计阶段",true,"考点:设计阶段进度控制的意义。工程设计要划分为初步设计和施工图设计两个阶段，特别复杂的工程设计还要增加技术设计阶段。参见教材P110。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]