[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108301":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108301,783,1,"单选题","在建设工程设计阶段属于监理单位的设计进度控制措施为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定设计委托方式及设计合同形式",false,{"key":16,"text":17,"correct":14},"B","编制指导性施工总进度计划并控制其实施",{"key":19,"text":20,"correct":21},"C","落实项目监理机构中专门负责设计进度控制的人员",true,{"key":23,"text":24,"correct":14},"D","建立健全设计技术经济定额及设计工作责任制","考点:监理单位在设计阶段的进度监控的内容。监理单位受业主的委托进行工程设计监理时，应落实项目监理班子中专门负责设计进度控制的人员。参见教材P114。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]