[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108299,783,1,"单选题","下列设计进度控制工作中，属于监理单位进度监控工作的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","认真实施设计进度计划",false,{"key":16,"text":17,"correct":14},"B","编制切实可行的设计总进度计划",{"key":19,"text":20,"correct":14},"C","编制阶段性设计进度计划",{"key":22,"text":23,"correct":24},"D","定期比较分析设计完成情况与计划进度",true,"考点:监理单位的进度监控。在进度计划实施过程中，监理工程师应定期检查设计工作的实际完成情况，并与计划进度进行比较分析。参见教材P114",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]