[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108298,783,1,"单选题","为履行设计合同，按期提交施工图设计文件，设计单位应尽量避免“三边”设计，下列不属于“三边”设计内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","边设计",false,{"key":16,"text":17,"correct":14},"B","边准备",{"key":19,"text":20,"correct":14},"C","边施工",{"key":22,"text":23,"correct":24},"D","边使用",true,"考点:设计单位的进度控制。坚持按基本建设程序办事，尽量避免进行“边设计、边准备、边施工”的“三边”设计。参见教材P114",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]