[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108294,783,1,"单选题","在设计过程中，如果业主改变其建设意图和要求，就会引起设计单位的设计变更，这是影响设计进度的（ ）因素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设意图和要求改变的影响",true,{"key":16,"text":17,"correct":18},"B","设计各专业之间协调配合的影响",false,{"key":20,"text":21,"correct":18},"C","工程变更的影响",{"key":23,"text":24,"correct":18},"D","材料代用.设备选用失误的影响","考点:影响设计进度的因素。建设意图及要求改变的影响：建设工程设计是本着业主的建设意图和要求而进行的，所有的工程设计必然是业主意图的体现。因此，在设计过程中，如果业主改变其建设意图和要求，就会引起设计单位的设计变更，必然会对设计进度造成影响。参见教材P113。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]