[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108293":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108293,783,1,"单选题","若发现进度拖后，（ ）应督促设计单位采取有效措施加快进度。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":21},"C","监理工程师",true,{"key":23,"text":24,"correct":14},"D","设计单位","考点:设计阶段进度控制工作程序。若发现进度拖后，监理工程师应督促设计单位采取有效措施加快进度。参见教材P111。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]