[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108292,783,1,"单选题","由（ ）持建设项目的批准文件和确定的建设用地通知书，向城市规划管理部门申请确定拟建项目的规划设计条件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","设计单位","考点:设计进度控制分阶段目标。由建设单位持建设项目的批准文件和确定的建设用地通知书，向城市规划管理部门申请确定拟建项目的规划设计条件。参见教材P112",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]