[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108290":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108290,783,1,"单选题","下列关于设计阶段进度控制的意义的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计进度控制是建设工程进度控制的前提",false,{"key":16,"text":17,"correct":14},"B","设计进度控制是施工进度控制的基础",{"key":19,"text":20,"correct":14},"C","设计进度控制是设备供应进度控制的重要内容",{"key":22,"text":23,"correct":24},"D","设计进度控制是材料供应进度控制的前提",true,"考点:设计阶段进度控制的意义。设计阶段进度控制的意义包括：（1）设计进度控制是建设工程进度控制的重要内容；（2）设计进度控制是施工进度控制的前提；（3）设计进度控制是设备和材料供应进度控制的前提。参见教材P110",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]