[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108289,783,1,"单选题","下列选项中，属于设计阶段进度控制主要任务的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期控制",false,{"key":16,"text":17,"correct":18},"B","出图控制",true,{"key":20,"text":21,"correct":14},"C","投资控制",{"key":23,"text":24,"correct":14},"D","质量控制","考点:设计阶段进度控制工作程序。建设工程设计阶段进度控制的主要任务是出图控制，也就是通过采用有效措施使工程设计者如期完成初步设计、技术设计、施工图设计等各阶段的设计工作，并提交相应的设计图纸及说明。参见教材P110。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]