[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108288,783,1,"单选题","实施建设工程所需要的设备和材料是根据设计而来的。设计单位必须提出（ ），以便进行加工订货或购买。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采购清单",false,{"key":16,"text":17,"correct":18},"B","设备清单",true,{"key":20,"text":21,"correct":14},"C","设备资料",{"key":23,"text":24,"correct":14},"D","采购资料","考点:设计阶段进度控制的意义。实施建设工程所需要的设备和材料是根据设计而来的。设计单位必须提出设备清单，以便进行加工订货或购买。参见教材P110。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]