[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108284,783,1,"单选题","在建设工程进度监测过程中，定期收集进度报表资料情况属于（ ）的主要方式。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际进度与计划进度的对比分析",false,{"key":16,"text":17,"correct":14},"B","实际进度数据的加工处理",{"key":19,"text":20,"correct":21},"C","进度计划执行中的跟踪检查",true,{"key":23,"text":24,"correct":14},"D","实际进度数据的统计分析","考点:进度监测的系统过程。对进度计划的执行情况进行跟踪检查是计划执行信息的主要来源，是进度分析和调整的依据，也是进度控制的关键步骤。跟踪检查的主要工作是定期收集反映工程实际进度的有关数据。为了全面、准确地掌握进度计划的执行情况，监理工程师应认真做好以下三方面的工作：（1）定期收集进度报表资料；（2）现场实地检查工程进展情况；（3）定期召开现场会议。参见教材P90。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]