[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108283,783,1,"单选题","下列工作内容中，属于进度监测系统过程的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分析进度偏差产生的原因",false,{"key":16,"text":17,"correct":14},"B","提出调整进度计划的措施",{"key":19,"text":20,"correct":21},"C","现场实地检查工程进度情况",true,{"key":23,"text":24,"correct":14},"D","分析进度偏差对总工期的影响","考点:进度监测的系统过程。跟踪检查的主要工作是定期收集反映工程实际进度的有关数据。为了全面、准确地掌握进度计划的执行情况，监理工程师应认真做好以下三方面的工作：（1）定期收集进度报表资料；（2）现场实地检查工程进展情况；（3）定期召开现场会议。参见教材P90。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]