[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108281,783,1,"单选题","进度计划实施过程中，一旦发现进度偏差，应采取措施对进度计划进行调整，下列工作中不属于进度调整系统过程的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对实际进度数据进行加工处理",true,{"key":16,"text":17,"correct":18},"B","分析进度偏差产生的原因",false,{"key":20,"text":21,"correct":18},"C","采取措施调整进度计划",{"key":23,"text":24,"correct":18},"D","分析进度偏差对后续工作和总工期的影响","考点:进度调整的系统过程。进度调整的系统过程包括：分析进度偏差产生的原因、分析进度偏差对后续工作和总工期的影响、确定后续工作和总工期的限制条件、采取措施调整进度计划、实施调整后的进度计划。参见教材P91。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]