[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108280,783,1,"单选题","在建设工程进度计划执行过程中，出现进度偏差后进行进度调整，分析进度偏差对后续工作和总工期的影响的前一个步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析进度偏差产生的原因",true,{"key":16,"text":17,"correct":18},"B","分析进度偏差对后续工作和总工期的影响",false,{"key":20,"text":21,"correct":18},"C","确定后续工作和总工期的限制条件",{"key":23,"text":24,"correct":18},"D","采取措施调整进度计划","考点:进度调整的系统过程。进度调整的系统过程是：（1）分析进度偏差产生的原因；（2）分析进度偏差对后续工作和总工期的影响；（3）确定后续工作和总工期的限制条件；（4）采取措施调整进度计划；（5）实施调整后的进度计划。参见教材P91",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]