[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108279":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108279,783,1,"单选题","在建设工程进度调整的系统过程中，当工作实际进度偏差影响到后续工作及总工期而需要采取措施调整进度计划时，首先需要进行的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定可调整进度的范围",true,{"key":16,"text":17,"correct":18},"B","进行调整措施的技术经济分析",false,{"key":20,"text":21,"correct":18},"C","进行调整方案的比选论证",{"key":23,"text":24,"correct":18},"D","分析进度偏差产生的原因","考点:进度调整的系统过程。当出现的进度偏差影响到后续工作或总工期而需要采取进度调整措施时，应当首先确定可调整进度的范围，主要指关键节点、后续工作的限制条件以及总工期允许变化的范围。参见教材P91。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]