[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108277,783,1,"单选题","当采用匀速进展横道图比较工作实际进度与计划进度时，如果表示实际进度的横道线右端落在检查日期的左侧，则表明（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际进度超前",false,{"key":16,"text":17,"correct":18},"B","实际进度拖后",true,{"key":20,"text":21,"correct":14},"C","实际进度与计划进度一致",{"key":23,"text":24,"correct":14},"D","无法说明实际进度与计划进度的关系","考点:横道图比较法。采用匀速进展横道图时，如果涂黑的粗线右端落在检查日期左侧，表明实际进度拖后。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]