[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108275,783,1,"单选题","（ ）是以横坐标表示时间，纵坐标表示累计完成任务量，绘制一条按计划时间累计完成任务量的曲线。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","S曲线比较法",true,{"key":16,"text":17,"correct":18},"B","香蕉曲线比较法",false,{"key":20,"text":21,"correct":18},"C","前锋线比较法",{"key":23,"text":24,"correct":18},"D","横道图比较法","考点:S曲线比较法。S曲线比较法是以横坐标表示时间，纵坐标表示累计完成任务量，绘制一条按计划时间累计完成任务量的S曲线。参见教材P95。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]