[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108273":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108273,783,1,"单选题","下列对于S曲线比较法的描述中，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","如果工程实际进展点落在计划S曲线左侧，表明此时实际进度比计划进度拖后",false,{"key":16,"text":17,"correct":14},"B","如果工程实际进展点落在S计划曲线右侧，表明此时实际进度比计划进度超前",{"key":19,"text":20,"correct":21},"C","如果工程实际进展点正好落在计划S曲线上，则表示此时实际进度与计划进度一致",true,{"key":23,"text":24,"correct":14},"D","在S曲线比较图中无法直接读出实际进度比计划进度超额或拖欠的任务量","考点:S曲线比较法。选项A错误，如果工程实际进展点落在计划S曲线左侧，表明此时实际进度比计划进度超前；选项B错误，如果工程实际进展点落在S计划曲线右侧，表明此时实际进度拖后；选项D错误，在S曲线比较图中可直接读出实际进度比计划进度超额或拖欠的任务量。参见教材P97。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]