[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108269":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108269,783,1,"单选题","下列关于列表比较法的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如果工作尚有总时差与原有总时差相等，说明该工作实际进度与计划进度一致",true,{"key":16,"text":17,"correct":18},"B","如果工作尚有总时差大于原有总时差，说明该工作实际进度拖后",false,{"key":20,"text":21,"correct":18},"C","如果工作尚有总时差小于原有总时差，且仍为非负值，说明该工作实际进度超前",{"key":23,"text":24,"correct":18},"D","如果工作尚有总时差小于原有总时差，且为负值，说明该工作实际进度拖后，但不影响总工期","考点:列表比较法。选项B错误，如果工作尚有总时差大于原有总时差，说明该工作实际进度超前，超前的时间为二者之差；选项C错误，如果工作尚有总时差小于原有总时差，且仍为非负值，说明该工作实际进度拖后，拖后的时间为二者之差，但不影响总工期；选项D错误，如果工作尚有总时差小于原有总时差，且为负值，说明该工作实际进度拖后，拖后的时间为二者之差，此时工作实际进度偏差将影响总工期。参见教材P102。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]