[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108268,783,1,"单选题","分析进度偏差是否超过总时差、自由时差时，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作的进度偏差大于该工作的总时差，则此进度偏差不影响其后续工作和总工期",true,{"key":16,"text":17,"correct":18},"B","工作的进度偏差未超过该工作的总时差，则此进度偏差不影响总工期",false,{"key":20,"text":21,"correct":18},"C","工作的进度偏差大于该工作的自由时差，则此进度偏差将对其后续工作产生影响",{"key":23,"text":24,"correct":18},"D","工作的进度偏差未超过该工作的自由时差，则此进度偏差不影响后续工作","考点:分析进度偏差对后续工作及总工期的影响。工作的进度偏差大于该工作的总时差，则此进度偏差必将影响其后续工作和总工期。参见教材P103",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]