[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108267,783,1,"单选题","在工程网络计划执行过程中，如果某项工作的进度偏差超过其自由时差，则该工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际进度影响工程总工期",false,{"key":16,"text":17,"correct":18},"B","实际进度影响其紧后工作的最早开始时间",true,{"key":20,"text":21,"correct":14},"C","由非关键工作转变为关键工作",{"key":23,"text":24,"correct":14},"D","总时差大于零","考点:分析进度偏差对后续工作及总工期的影响。如果工作的进度偏差大于该工作的自由时差，则此进度偏差将对其后续工作产生影响，此时应根据后续工作的限制条件确定调整方法；如果工作的进度偏差未超过该工作的自由时差，则此进度偏差不影响后续工作，因此，原进度计划可以不作调整。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]