[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108266,783,1,"单选题","在工程网络计划的实施过程中，如果需要确定某项工作进度偏差对紧后工作最早开始时间的影响程度，应根据（ ）的差值进行确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差与进度偏差",true,{"key":16,"text":17,"correct":18},"B","总时差与进度偏差",false,{"key":20,"text":21,"correct":18},"C","自由时差与总时差",{"key":23,"text":24,"correct":18},"D","时间间隔与进度偏差","考点:分析进度偏差对后续工作及总工期的影响。如果工作的进度偏差大于该工作的自由时差，则此进度偏差将对其后续工作产生影响，此时应根据后续工作的限制条件确定调整方法；如果工作的进度偏差未超过该工作的自由时差，则此进度偏差不影响后续工作，因此，原进度计划可以不作调整。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]