[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108265":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108265,783,1,"单选题","某工程网络计划中，C工作的总时差为8d，自由时差为5d，在检查实际进度时，发现该工作的持续时间延长了6d，则说明C工作的实际进度将使其紧后工作的最早开始时间推迟（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6d，同时使总工期延长6d",false,{"key":16,"text":17,"correct":14},"B","1d，同时使总工期延长1d",{"key":19,"text":20,"correct":14},"C","6d，同时使总工期延长1d",{"key":22,"text":23,"correct":24},"D","1d，但不影响总工期",true,"考点:分析进度偏差对后续工作及总工期的影响。如果工作的进度偏差未超过该工作的总时差，则此进度偏差不影响总工期。如果工作的进度偏差大于该工作的自由时差，则此进度偏差将对后续工作产生影响。自由时差为5d，该工作延长了6d，所以影响后续工作6-5=1d。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]