[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108263":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108263,783,1,"单选题","当某项工作实际进度拖延的时间超过其总时差而需要调整进度计划时，应考虑该工作的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资源需求量",false,{"key":16,"text":17,"correct":18},"B","后续工作的限制条件",true,{"key":20,"text":21,"correct":14},"C","自由时差的大小",{"key":23,"text":24,"correct":14},"D","紧后工作的数量","考点:进度计划的调整方法。当某项工作实际进度拖延的时间超过其总时差而需要对进度计划进行调整时，除需考虑总工期的限制条件外，还应考虑网络计划中后续工作的限制条件，特别是对总进度计划的控制更应注意这一点。参见教材P108。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]