[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108260,783,1,"单选题","某工程时标网络计划及第7周末前锋线如下图所示，关于实际进度与计划进度比较结果正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作C实际进度拖后2周，影响总工期1周",false,{"key":16,"text":17,"correct":14},"B","工作D实际进度提前1周，不影响总工期",{"key":19,"text":20,"correct":21},"C","工作F实际进度提前1周，不影响总工期",true,{"key":23,"text":24,"correct":14},"D","如果按照第7周末结果调整进度计划，工作H可提前开始","考点:前锋线比较法。选项A错误，工作C实际进度拖后3周，影响总工期1周；选项B错误，工作D实际进度拖后1周，影响总工期1周；选项D错误，如果按照第7周末结果调整进度计划，工作H不能提前开始。参见教材P101。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]