[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108259,783,1,"单选题","下列方法中，既能比较工作的实际进度与计划进度，又能分析工作的进度偏差对工程总工期影响程度的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","匀速进度横道图比较法",false,{"key":16,"text":17,"correct":14},"B","S曲线比较法",{"key":19,"text":20,"correct":14},"C","非匀速进展横道图比较法",{"key":22,"text":23,"correct":24},"D","前锋线比较法",true,"考点:前锋线比较法。横道图比较法（包括匀速进展横道图比较法和非匀速进展横道图比较法）适用于工程项目中各项工作实际进度与计划进度的比较；前锋线比较法不仅可以判定工程项目中各项工作的进度偏差，而且可以进一步分析工作进度偏差对工程总工期的影响；S曲线比较法只能将工程项目作为一个整体进行实际进度与计划进度的比较。参见教材P100。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]