[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108258,783,1,"单选题","已知时标网络计划的前锋线进行实际进度与计划进度比较如图所示，则（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","第5天检查时，发现A还没有完成工作",false,{"key":16,"text":17,"correct":14},"B","第5天检查时，发现B已完成工作",{"key":19,"text":20,"correct":14},"C","第5天检查时，发现D已开工1天",{"key":22,"text":23,"correct":24},"D","第5天检查时，发现C已进行2天",true,"考点:前锋线比较法。工作实际进展位置点落在检查日期左侧，表明该工作实际进度拖后；落在检查日期右侧，表明该工作实际进度超前；与检查日期重合，表明该工作实际进度与计划进度一致。本题A已经完成；B落后1天，还没有完成；C按计划进度，已经开始2天；D落后2天，还没有开始。参见教材P101",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]