[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108257,783,1,"单选题","某分部工程时标网络计划如下图所示。当该计划执行到第5天结束时检查实际进展情况，实际进度前锋线中表述错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作C实际进度拖后2天，并影响总工期1天",false,{"key":16,"text":17,"correct":18},"B","工作D尚有总时差1天",true,{"key":20,"text":21,"correct":14},"C","工作E拖后1天，将影响总工期1天",{"key":23,"text":24,"correct":14},"D","工作G的最早开始时间将受影响","考点:前锋线比较法。第5天结束时，工作C拖后2天，其总时差为1天，影响总工期1天；工作D进度正常，其总时差尚有2天；工作E进度拖后1天，其为关键工作，影响总工期1天；由于工作G的最早开始时间受到工作C拖后的影响；工作H的最早开始时间会受到工作E拖后1天的影响。参见教材P101。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]