[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108256,783,1,"单选题","某工程双代号时标网络计划如下图所示，根据第6周末实际进度检查结果绘制的前锋线如点划线所示，通过比较可以看出（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","C工作实际进度拖后2周，影响工期2周",false,{"key":16,"text":17,"correct":14},"B","D工作实际进度超前2周，不影响工期",{"key":19,"text":20,"correct":21},"C","D工作实际进度拖后3周，影响工期2周",true,{"key":23,"text":24,"correct":14},"D","E工作实际进度拖后1周，不影响工期","考点:前锋线比较法。C工作实际进度拖后2周，其总时差为1周，所以影响工期1周。D工作实际进度拖后3周，其总时差为1周，所以影响总工期2周。E工作实际进度拖后1周，其总时差为0周，影响总工期1周。参见教材P101。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]