[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108255,783,1,"单选题","在列表比较法中若工作尚有总时差小于原有总时差，且为非负值，其表示的含义为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","说明工作的实际进度与计划进度一致",false,{"key":16,"text":17,"correct":18},"B","说明该工作的实际进度比计划进度拖后，但不影响工期",true,{"key":20,"text":21,"correct":14},"C","说明该工作的实际进度比计划进度拖后，且影响工期",{"key":23,"text":24,"correct":14},"D","说明该工作的实际进度比计划进度超前，但不影响工期","考点:列表比较法。如果工作尚有总时差小于原有总时差，且为非负值，说明该工作实际进度拖后，拖后的时间为二者之差，但不影响总工期。参见教材P102。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]