[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108252":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108252,783,1,"单选题","已知某网络计划中工作M的自由时差为1天，总时差为4天。通过检查分析，发现该工作的实际进度拖后，且影响总工期2天。在其它工作均正常的前提下，工作M的实际进度拖后（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","6",true,"考点:进度偏差对后续工作及总工期的影响。由条件可知影响总工期，则工作M的拖后超过了总时差。工作M的实际进度拖后4+2=6（天）。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]