[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108251":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108251,783,1,"单选题","在工程实际的执行过程中往往造成实际进度与计划进度的偏差，则在项目进度计划中应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","偶有偏差不足为怪",false,{"key":16,"text":17,"correct":14},"B","将实际进度调整到计划进度",{"key":19,"text":20,"correct":14},"C","废除计划进度",{"key":22,"text":23,"correct":24},"D","采取有效的监测手段不断发现问题，以及应用行之有效的进度调整方法及时解决问题",true,"考点:进度监测的系统过程。在进度计划的执行过程中，必须采取有效的监测手段对进度计划的实施过程进行监控，以便及时发现问题，并运用行之有效的进度调整方法来解决问题。参见教材P90",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]