[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108249,783,1,"单选题","下列工作中，属于建设工程进度监测系统过程中工作内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析进度偏差产生的原因",false,{"key":16,"text":17,"correct":18},"B","实际进度数据的加工处理",true,{"key":20,"text":21,"correct":14},"C","确定后续工作和总工期的限制条件",{"key":23,"text":24,"correct":14},"D","分析进度偏差对后续工作的影响","考点:进度监测的系统过程。进度监测系统过程主要包括：（1）进度计划执行中的跟踪检查；（2）实际进度数据的加工处理；（3）实际进度与计划进度的对比分析。选项ACD属于进度调整的系统过程内容。参见教材P90",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]