[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108247":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108247,783,1,"单选题","通过缩短某些工作的持续时间调整施工进度计划时，其主要特点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在非关键线路上缩短工作持续时间",false,{"key":16,"text":17,"correct":14},"B","采用平行作业方式加快施工进度",{"key":19,"text":20,"correct":21},"C","不改变工作之间的先后顺序关系",true,{"key":23,"text":24,"correct":14},"D","保持网络计划中关键工作不变","考点:进度计划的调整方法。缩短某些工作的持续时间：不改变工程项目中各项工作之间的逻辑关系，而通过采取增加资源投入、提高劳动效率等措施来缩短某些工作的持续时间，使工程进度加快，以保证按计划工期完成该工程项目。压缩关键线路和超过计划工期的非关键线路上的工作。参见教材P104。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]