[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108246":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108246,783,1,"单选题","调整建设工程进度计划时，下列（ ）不能改变某些工作之间的逻辑关系。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织平行作业",false,{"key":16,"text":17,"correct":14},"B","组织搭接作业",{"key":19,"text":20,"correct":14},"C","组织流水作业",{"key":22,"text":23,"correct":24},"D","加大资源投入",true,"考点:进度计划的调整方法。将顺序进行的工作改为平行作业、搭接作业以及分段组织流水作业等，都可以有效地缩短工期，改变工作之间的逻辑关系。参见教材P104。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]