[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108245":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108245,783,1,"单选题","在建设工程进度计划执行过程中，当出现的进度偏差影响到后续工作或总工期而需要采取进度调整措施时，应当首先（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定可调整进度的范围",true,{"key":16,"text":17,"correct":18},"B","确定可利用的资源数量",false,{"key":20,"text":21,"correct":18},"C","分析所采取措施的成本",{"key":23,"text":24,"correct":18},"D","分析比较各种措施的优劣","考点:进度调整的系统过程。进度调整的系统过程是：（1）分析进度偏差产生的原因；（2）分析进度偏差对后续工作和总工期的影响；（3）确定后续工作和总工期的限制条件；（4）采取措施调整进度计划；（5）实施调整后的进度计划。当出现的进度偏差影响到后续工作或总工期而需要采取进度调整措施时，应当首先确定可调整进度的范围，主要指关键节点、后续工作的限制条件以及总工期允许变化的范围。参见教材P91",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]