[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108243,783,1,"单选题","采取进度调整措施，应以（ ）的限制条件为依据，确保要求的进度目标得到实现。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","紧前工作和总工期",false,{"key":16,"text":17,"correct":14},"B","平行工作和总工期",{"key":19,"text":20,"correct":21},"C","后续工作和总工期",true,{"key":23,"text":24,"correct":14},"D","紧前工作和后续工作","考点:进度调整的系统过程。采取进度调整措施，应以后续工作和总工期的限制条件为依据，确保要求的进度目标得到实现。参见教材P91",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]