[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108242,783,1,"单选题","当采用匀速进展横道图比较法比较工作实际进度与计划进度时，如果表示工作实际进度的横道线右端点落在检查日期的右侧，则检查日期与该横道线右端点的差距表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度超前的时间",true,{"key":16,"text":17,"correct":18},"B","超额完成的任务量",false,{"key":20,"text":21,"correct":18},"C","进度拖后的时间",{"key":23,"text":24,"correct":18},"D","尚待完成的任务量","考点:横道图比较法。在匀速进展横道图中，用涂黑的粗线表示实际进度，如果涂黑的粗线的右端落在检查日期的右侧时，表示实际进度超前。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]