[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108241":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108241,783,1,"单选题","某工作的实际进度与计划进度如下图所示，下列描述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第2周末本工作实际完成的任务量小于计划任务量",true,{"key":16,"text":17,"correct":18},"B","第1周内实际进度提前2%",false,{"key":20,"text":21,"correct":18},"C","第4周内实际进度拖后5%",{"key":23,"text":24,"correct":18},"D","第3周末实际进度拖后2%","考点:横道图比较法。选项B错误，第1周内实际进度拖后2%；选项C错误，第4周内实际完成18%，计划完成20%，因此第4周内实际进度拖后2%；选项D错误，第3周末实际进度拖后3%。参见教材P94。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]