[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108240,783,1,"单选题","某钢筋工程计划用7周完成，每周计划和实际累计完成任务量如下图所示。关于该工程进度比较结果的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际开始时间晚于计划开始时间1周",false,{"key":16,"text":17,"correct":14},"B","第2周末实际进度比计划进度提前5%",{"key":19,"text":20,"correct":21},"C","第4周实际进度比计划进度拖后10%",true,{"key":23,"text":24,"correct":14},"D","第5周起中断2周","考点:横道图比较法。选项A错误，实际开始时间晚于计划开始时间0.5周；选项B错误，第2周末实际进度比计划进度拖后5%；选项D错误，该进度横道图没有比较第5周以后的进度。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]