[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108239,783,1,"单选题","某混凝土工程按计划12天完成，下图中标出了截止至第7天末的实际施工时间，从图中可以看出（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该工作实际开始时间比计划开始时间晚2天",false,{"key":16,"text":17,"correct":14},"B","第5天末实际进度比计划进度拖后3%",{"key":19,"text":20,"correct":14},"C","第4天内计划完成的任务量为11%",{"key":22,"text":23,"correct":24},"D","第7天末实际进度比计划进度拖后5%",true,"考点:横道图比较法。选项A错误，该工作实际开始时间比计划开始时间晚1.5天；选项B错误，第5天末实际进度比计划进度超前3%；选项C错误，第4天内计划完成的任务量为12%。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]